The Tabqa Electricity Department, in cooperation with Al Jarnia Electricity Group, began implementing support and rehabilitation works for the electrical network in a number of villages in the district, with the aim of improving the stability of the electrical supply and reducing the loads on the transformers.
The works included increasing the capacity of the Al-Jumaat village transformer from 50 to 100 kva, which contributes to meeting the needs of approximately 1,000 villagers, in addition to redistributing transformers between villages to achieve optimal utilization and improve service efficiency.
In this context, the replaced transformer was transferred to the village of Al-Mahnawi to replace a transformer with a smaller capacity, while the Al-Mahnawi transformer was transferred to the village of Al-Thlath Khrab to replace a transformer that had stopped working for more than two weeks.
The broken transformer was also transferred to the Tabqa Electricity Department to carry out the necessary maintenance work, in parallel with carrying out maintenance work for the internal networks in Al Jarnia district, with the aim of improving the quality and stability of the electrical service provided to citizens.