Home Al-Raqqa

Intensive maintenance and rehabilitation of electrical transformer stations in Raqqa to improve network stability

21/05/2026
in Al-Raqqa
A A
Intensive maintenance and rehabilitation of electrical transformer stations in Raqqa to improve network stability
25
VIEWS
شارك على فيسبوكغرد على X

This post is also available in: العربية

Engineering and technical teams continue maintenance and rehabilitation work at electrical transformer stations in Raqqa Governorate, with the participation of a technical and engineering team from the Damascus Electricity Corporation, as part of efforts aimed at raising the readiness of the stations and improving the stability of the electrical network in the city and its countryside.

The work included carrying out maintenance on 20 kV medium voltage cells at the Al-Foroseyah conversion station, in addition to conducting a technical inspection of 20 kV cells at the Raqqa 1, Raqqa 2, and Raqqa 3 conversion stations, in addition to the Bir Al-Hashm station.

The action plan aims to rehabilitate electrical cells and address faults and technical observations, which will contribute to enhancing the reliability of electrical supply and improving the level of service provided to citizens in Raqqa Governorate and its countryside

Tags: Raqqa
ShareTweetSendShare
Previous Post

Deir Ezzor Water Corporation continues to maintain Al-Jazeera stations with support from the “Furat” program

Next Post

Farmers in Hasakah block Tal Abyad road in protest over lack of agricultural diesel allocations

🧐

Raqqa Health intensifies medication control and closes violating pharmacies

Raqqa Health intensifies medication control and closes violating pharmacies

18/07/2026
qa Justice destroys 200 kg of narcotic substances seized as part of security campaigns

qa Justice destroys 200 kg of narcotic substances seized as part of security campaigns

15/07/2026
Raqqa City Council continues to rehabilitate the road opposite Al-Hayat Hospital as part of the road maintenance plan

Raqqa City Council continues to rehabilitate the road opposite Al-Hayat Hospital as part of the road maintenance plan

16/07/2026
Load More

Leave a Reply

Your email address will not be published. Required fields are marked *

four × 1 =

  • أكثر من 33 ألف طن من القمح في صوامع خس عالج بالرقة

    أكثر من 33 ألف طن من القمح في صوامع خس عالج بالرقة

    1 shares
    Share 0 Tweet 0
  • استكمال أعمال صيانة طريق دير الزور – الرقة وتحسين المقاطع الأكثر تضرراً

    1 shares
    Share 0 Tweet 0
  • Launching of a training workshop to develop union capabilities for Deir Ezzor workers with the participation of three governorates

    1 shares
    Share 0 Tweet 0
  • 40 homes were inspected in Al-Huwaiqah neighborhood in preparation for their restoration, with support from the Al-Birr Wal-Ihsan Association

    1 shares
    Share 0 Tweet 0
  • Launching of a training workshop to develop union capabilities for Deir Ezzor workers with the participation of three governorates

    1 shares
    Share 0 Tweet 0
Launching of a training workshop to develop union capabilities for Deir Ezzor workers with the participation of three governorates
Deir ez-Zor City

Launching of a training workshop to develop union capabilities for Deir Ezzor workers with the participation of three governorates

by Editorial Board
20/07/2026
0

...

Read moreDetails
40 homes were inspected in Al-Huwaiqah neighborhood in preparation for their restoration, with support from the Al-Birr Wal-Ihsan Association

40 homes were inspected in Al-Huwaiqah neighborhood in preparation for their restoration, with support from the Al-Birr Wal-Ihsan Association

20/07/2026
The start of the rehabilitation project for  Al-Furat central mill in Deir Ezzor

The start of the rehabilitation project for Al-Furat central mill in Deir Ezzor

19/07/2026
Termination of the investment contract for the Al-Tebni bakery in Deir Ezzor after monitoring food and health violations

Termination of the investment contract for the Al-Tebni bakery in Deir Ezzor after monitoring food and health violations

19/07/2026
Reconnecting the second generation group at the Kdiran Dam to the electrical grid after completing its periodic maintenance

Reconnecting the second generation group at the Kdiran Dam to the electrical grid after completing its periodic maintenance

18/07/2026
  • Featured news
  • Interviews
  • Studies
  • Articles
  • Info Graphic
  • Reports
  • Maps
  • Forefathers land
  • Press
  • Photos from Homeland
  • Video Graphic
  • D24 Magazine
Designed and developed by 

DeirezZor24: Speaking Reality, Building Awareness

No Result
View All Result
  • Featured news
  • News
    • Eastern countryside
    • Deir ez-Zor City
    • Eastern & western countryside
    • Western countryside
    • Northern countryside
  • Reports
  • Violations
    • Daesh
    • Syrian regime
  • العربية

DeirezZor24: Speaking Reality, Building Awareness