This post is also available in:
Engineering and technical teams continue maintenance and rehabilitation work at electrical transformer stations in Raqqa Governorate, with the participation of a technical and engineering team from the Damascus Electricity Corporation, as part of efforts aimed at raising the readiness of the stations and improving the stability of the electrical network in the city and its countryside.
The work included carrying out maintenance on 20 kV medium voltage cells at the Al-Foroseyah conversion station, in addition to conducting a technical inspection of 20 kV cells at the Raqqa 1, Raqqa 2, and Raqqa 3 conversion stations, in addition to the Bir Al-Hashm station.
The action plan aims to rehabilitate electrical cells and address faults and technical observations, which will contribute to enhancing the reliability of electrical supply and improving the level of service provided to citizens in Raqqa Governorate and its countryside