The General Corporation for Road Transport continues to implement rehabilitation works on the Al-Seyasya Bridge in Deir Ezzor city, while achieving significant progress in various phases of the project in accordance with the approved executive program.
The Foundation explained that the work is currently focused on four main activities, with the completion rate of the reinforced concrete works for the pillars reaching 55%, and they are expected to be completed within 20 days.
The completion rate of the construction and equipping of the bridge crane has reached 95%, while the manufacturing rate of the metal forms for the main load-bearing bridges has reached 90%, and they will be delivered within three days.
The Corporation indicated that the work of detailing and preparing the construction steel for bridges has reached a completion rate of about 7%, with work continuing at an accelerated pace to complete the various stages of the project within the specified timetable.
The Syrian Foundation for Building and Construction is implementing the bridge rehabilitation project, in accordance with the approved executive program.