In an important step to revive the irrigation system and support the agricultural sector in Al-Hasakah Governorate, the Water Resources Directorate has completed the preparation of the Al Kawsiya gate in the southern dam, known as «Al-Khabur Bed Intake», after an interruption that lasted about 15 years, in an achievement that would restore hope to thousands of farmers in the area.

The implemented works included equipping the gate and conducting manual and automated operational tests and experiments, in preparation for resuming water pumping through the outlet, with a flow capacity of up to 130 cubic metres, which contributes to enhancing the access of irrigation water to the beneficiary agricultural lands.

The operation of the gate is expected to positively impact the agricultural situation in the area, by providing irrigation water for approximately 12,000 hectares of agricultural land along both banks of the Khabur River. This will support agricultural activity, improve production opportunities, and reduce farmers’ suffering associated with the shortage of water resources.

The importance of this step is not limited to restarting a water facility that has been out of service for many years, but rather represents an important beginning in the process of rehabilitating the irrigation system infrastructure and utilizing available water resources to serve agricultural and economic stability in the Hasakah countryside.

While farmers wait for the return of water flow to their lands, the rehabilitation of the «Khabur Bed Intake» represents a glimmer of hope for the return of life to large areas of agricultural land, enhancing local production, and improving the living conditions of families who depend on agriculture as a major source of livelihood.